1. OBJECTIVE:
To
provide guidelines for cleaning and storage of personal protective equipments.
2. INTRODUCTION:
The personal protective
equipments are very useful and valuable tools as far as safety of personnel and
products are concerned. It is not just enough that people know about their usage
, it is equally important that proper care should be taken in maintenance of
the equipments. The equipments should be cleaned properly and stored in secure
places assigned for them to prevent misuse and damage. The cleaning procedure
should be devised for each and every type of PPE separately and personnel
should be instructed to follow the same.
3.
PROCEDURE:
A.
HAND GLOVES:
3.1.
Hand gloves should be thoroughly washed every evening after usage because they come
directly in
contact with material.
3.2.
First wash them with tap water followed by soap solution.
3.3.
Wash them with disinfectant solution followed by D.M.water.
3.4.
Dry them completely under the hand dryer and store in a closed container in a dust
free atmosphere.
B.
NOSE MASKS:
3.5.
Nose masks are two types. i.e., disposable type and filter type.
3.6.
The disposable masks should be cleaned every day by blowing air after usage and
should be
discarded immediately when they are damaged.
3.7.
Filter type nose masks have removable holders for filters. The filters have to
be removed from the holders and cleaned by air followed by water and dried.
PREPARED BY REVIEWED BY APPROVED BY
PRODUCTION EXECUTIVE PRODUCTION MANAGER
G.M - Q.A
SOP No. : 05/S
Page :
2 of 2
Version No :
07
C. OTHER TYPE OF PROTECTIVE
EQUIPMENTS LIKE FACE SHIELDS, GOGGLES, HELMETS, HEAT RESISTANT GLOVES &
RUBBER GLOVES ETC.:
All these equipments can be washed or cleaned
with wet cloth and dried.
4. RESPONSIBILITY : 1)
Stores Dept.
2)
All the Production Employees.
5. REVIEW
GUIDE :
SOP revised as per due date.
6. ANNEXURE : Log book.
7. SOPs DISTRIBUTION:
This SOP
shall be distributed to following Departments:
Name
of the Department
|
Master Copy
|
Circulatory Copy
|
QA/QC
|
√
|
X
|
Production
|
x
|
√
|
Warehouse
|
x
|
√
|
Administration
|
x
|
X
|
Maintenance
|
x
|
X
|
8. VERSION
HISTROY :
Revision number
|
Change
|
Revision
no 03 to 04
|
1. SOP format revised
2.
SOP revised as per due date.
|
Revision
no. 04 to 05
|
1.
SOP revised as per due date.
2.
SOP distribution table included in the SOP
|
Revision
no. 05 to 06
|
|
Version no. 06 to 07
|
|
PREPARED BY
REVIEWED BY APPROVED BY
PRODUCTION EXECUTIVE PRODUCTION MANAGER
G.M - Q.A
Comments
Post a Comment