1.0 OBJECTIVE:
To provide guidelines for Operation & Maintenance
of HPLC System.
2.0 POLICY:
To ensure establish a procedure for operation of HPLC
3.0 PROCEDURE:
3.1
Switch on the Power supply and UPS.
3.2
Switch on the Pump, Detector,
computer and Printer, allow to warm the system.
3.3
Check the Column fitted on the
system is suitable or not, if not install the required Column.
3.4
Wash the Column with washing
solution (methanol & water each) for 30 minutes.
3.5
Prepare the Mobile phase and degas
carefully.
3.6
Run the Mobile phase at required
flow rate to saturate the Column and check the baseline.
3.7
Set the required detector parameters
on Detector.
3.8 If the
base line is o.k. Then
set the required chromatogram parameters on Method file or run the injections
on default method first and set suitable parameters.
3.9 Prepare
the standard solutions and run five standard injections on the system and check
system suitability. The injecting sample does not have any air bubbles prior to
injection.
3.10 If the
RSD of the Standards chromatograms is less than two, then the system is
suitable for Sample injections. Otherwise repeat the Standard injections till
you get the RSD below two.
3.11 Inject
the required Sample and take the chromatograms and calculate the Percentage of
Active ingredient on the basis of respective peak areas.
PRIME MOVER CONCURRER APPROVER
EXECUTIVE (Q.A) PRODUCTION MANAGER G.M (Q.A)
|
SOP No.
: xxx
Page : 2 of 3
Revision No:xx
3.12
After completion of work, the Column
must be washed with wash solution for one hour.
3.13
For better performance of HPLC system
adhere to the following guidelines:
3.13.1 Use only HPLC grade chemicals.
3.13.2 Mobile phase and all solutions of HPLC must be
filtered and degassed.
3.13.3 Filter the standard and sample solutions using
0.45 micron nylon 66 membrane filter.
3.13.4 Do not operate the system above 3000psi.
User levels :
● Admin has the authority to access the process
of programming, new method creation, modifications
and Audit trails.
● While the users accessibility is restricted
to running and viewing and printing of
reports for the
purpose of analysis.
4.0 FREQUENCY: As and when
required.
5.0 RESPONSIBILITY:
Executive Q.A.
6.0 REVIEW
GUIDE: Log register &
Calibration register.
7.0 ANNEXURE:
-------
8.0 SOPs
DISTRIBUTION:
This
SOP shall be distributed to following Departments:
Name of the Department
|
Master Copy
|
Circulatory Copy
|
QA/QC
|
√
|
√
|
Production
|
x
|
X
|
Warehouse
|
x
|
X
|
General
|
x
|
X
|
Maintenance
|
x
|
X
|
PRIME MOVER CONCURRER APPROVER
EXECUTIVE (Q.A) PRODUCTION MANAGER G.M (Q.A)
|
SOP No.
: xxxx
Page : 3 of 3
Revision No :xx
9.0 REVISION
HISTROY :
Revision number
|
Change
|
Revision
no 06 to 07
|
1.
SOP format revised.
|
Revision
no 07 to 08
|
1.
SOP revised as per due date.
|
Revision
no 08 to 09
|
1. SOP revised as per due date.
2. Name of Prime Mover, Concurrer & Approver
included in the
SOP.
3. SOP Revision No. included in all
the annexures of SOP.
4.
Annexure subheading and details of annexures included in SOP.
|
Revision no 09 to 10
|
1.SOP
revised to include user levels in the SOP.
|
PRIME MOVER CONCURRER APPROVER