SANITIZATION & OPERATING PROCEDURE FOR PURIFIED WATER PLANT CIRCULATORY LOOP LINE


STANDARD OPERATING PROCEDURE


SUBJECT :                                            
SANITIZATION & OPERATING PROCEDURE FOR PURIFIED WATER PLANT CIRCULATORY LOOP LINE.
DEPARTMENT           : LIQUIDS
SOP NO.                      : xxx
Page No                       : 1 of 2
Effective Date                :xxxxx
Next Review                :xxxxx
Version No                  :xx

1.0       OBJECTIVE:

To provide guidelines for cleaning, sanitization and operating procedure for Purified water plant circulatory loop line system.

2.0       POLICY:
         
To avoid microbial contamination and to maintain the sanitized condition of purified water plant circulatory loop line.

3.0        PROCEDURE:

3.1  Collect Purified water in 1000 Ltr tank.
3.2   Shut down RO plant II.
3.3  Heat water with aid of steam in the 1000 Ltr tank upto 90-940C then start circulation of hot water in the loop line .Then temperature can be recorded from the display on the calibrated temperature controller.
3.4  Check the return water temperature display on the calibrated temperature controller. Return water temperature should reach upto 820C.
3.5    Circulate hot water at 820C  for 30 mins.
3.6  After the completion of  30 minutes sanitization the  hot water is drained.
 . 

4.0       FREQUENCY: Once in 15days.

5.0       RESPONSIBILITY: Operator / Maintenance executive.
                                               
6.0       ANNEXURE: Sanitization process temperature record.






                                                                                  






SOP No.          : 12/ ENG
Page                : 2 of 2
Version No      :xx
7.0       SOPs DISTRIBUTION:

            This SOP shall be distributed to following Departments:

Name of the Department
Master Copy
Circulatory Copy
QA/QC
x
Production
x
Warehouse
x
x
General
x
x
Maintenance
x
x


8.0       VERSION HISTORY:

Version number     
Change
Version no 00
 NEW SOP
Revision no 00 to 01
1. SOP revised before the due date to incorporate distribution table.
2. 3.C  numbered from 1 - 17
Version no 01 to 02
1. SOP revised as per due date.
2. Name of Prime Mover, Concurrer & Approver included in the  
    SOP.
3. SOP Revision No. included in all the annexures of SOP.
4. Annexure subheading and details of annexures included in SOP.
Version no 02 to 03
1.This SOP was 15/L earlier now included as 12/ENG without any change in the procedure.
                                    


 

Comments

Popular posts from this blog

STANDARD OPERATING PROCEDURE CALIBRATION OF SHIMADZU HPLC (LC-2010CHT)

STANDARD OPERATING PROCEDURE Operating and Maintenance Procedure for Cyclo Mixer

STANDARD OPERATING PROCEDURE LAB EQUIPMENT FTIR SPECTROPHOTOMETER – OPERATION AND CALIBRATION