1.0            OBJECTIVE:
1.1                   To lay down a procedure for monitoring and recording the temperature and Pressure Differential in Microbiology laboratory.
2.0            SCOPE:
2.1                   This procedure is applicable for monitoring and recording the temperature and Pressure Differential in microbiology laboratory at  Pharma Private Limited.
3.0            RESPONSIBILITY:
3.1                   Microbiologist/QC Designee: Responsible for monitoring and recording the temperature and Pressure Differential.
3.2                   Section In-charge: Responsible for review the procedure.
3.3                   QC Head: Responsible for implementing the procedure.
3.4                   QA Head: Overall compliance.     
4.0            PROCEDURE:
4.1                   Pressure Differential shall be recorded thrice in shift i.e., starting of the shift, afternoon or before micro activity carried out and ending of the shift for the following areas by using Magnehelic gauge.
4.1.1             Cool zone (84)
4.1.2             LAF - I (82)
4.1.3             LAF - II (83)
4.1.4             Culture Storage Area (81)
4.1.5             Corridor
4.1.6             Change Room II (79)
4.1.7             Micro Office (78)
4.1.8             Media Preparation Room (75 a)
4.1.9             Media storage room (80)
4.2                 Temperature shall be recorded thrice in shift i.e., starting of the shift, afternoon or before micro activity carried out and ending of the shift for the following areas by using Thermo Hygro meters.
4.2.1             Cool zone (84)
4.2.2             LAF - I (82)
4.2.3             LAF - II (83)
4.2.4             Culture Storage Area (81)
4.2.5             Incubator room (112a)
4.2.6             Media Preparation Room (75 a)
4.2.7             Media storage room (80)
4.3                 Temperature shall be entered in Annexure – I.
4.4                 Pressure Differential shall be entered in Annexure – II.
4.5                 The Acceptance criterion for temperature monitoring is NMT 25°C.
4.6                 The Acceptance criterion for pressure differential is NLT 0.6mm of water gauge.
4.7                   If any breakdown or maintenance of Thermohygro meter or Magnehelic gauge use standby thermo hygrometer or Magnehelic gauge for monitoring the temperature and pressure differentials.       
5.0            ABBREVIATIONS:
QC: Quality Control
QA: Quality Assurance
LAF: Laminar air flow
NLT: Not Less Than
SOP: Standard Operating Procedure
NMT: Not More Than


Comments

Popular posts from this blog

STANDARD OPERATING PROCEDURE CALIBRATION OF SHIMADZU HPLC (LC-2010CHT)

STANDARD OPERATING PROCEDURE Operating and Maintenance Procedure for Cyclo Mixer

STANDARD OPERATING PROCEDURE LAB EQUIPMENT FTIR SPECTROPHOTOMETER – OPERATION AND CALIBRATION