1.0 OBJECTIVE:
To provide guidelines for Operation & Maintenance
of Digital PH meter
2.0 POLICY:
To ensure establish a procedure for operating of
digital PH meter.
3.0 PROCEDURE:
3.1
Switch on the power supply and allow the instrument to warm up for 15 min.
3.2
PH
meter should always be in “Switch on mode” during working hours.
3.3 Switch
“on” the equipment. Remove the
electrode from the water; wipe out the water on the electrode using tissue
paper than rinse the electrode with CO2 free water than wipe out
with tissue paper.
3.4 Immerse
the electrode in one of the buffer solution, adjust the temperature control and
adjust the calibration control to the observed pH value identical with the
buffer solution under examination, by shaking it slowly.
3.1 Takeout
the electrode washed with CO2 free water, wipe it with tissue paper.
3.6 Repeat the procedure using second buffer
solution.
3.7 Place
the electrode the third buffer solution and check the pH without adjusting the
calibration control at same temperature.
3.8 Note
down the pH readings of the solutions in Calibration register before making
necessary adjustment.
3.9
The readings of all three buffers should
not differ more than 0.05 units.
3.10 If the
difference is more than 0.05 units examine the electrodes & if they are
faulty, replace the electrode.
3.11 Immerse
the electrode in PH 9.20 buffer solutions and
check the display value. If there is any error, adjust the knob to set to read PH 9.20.
3.12 Rinse
and wipe the electrode and immerse in the sample solution of which PH is to be measured and read the pH value on display.
3.13
Always keep the electrode immersed in
distilled water.
3.14
Standardize the instrument before use.
4.0 FREQUENCY: As and when
required.
5.0 RESPONSIBILITY:
Executive Q.A.
6.0 REVIEW GUIDE: Calibration register. Cross Check daily before use.
7.0 ANNEXURE:
-------
8.0 SOPs
DISTRIBUTION:
This
SOP shall be distributed to following Departments:
Name of the Department
|
Master Copy
|
Circulatory Copy
|
QA/QC
|
√
|
√
|
Production
|
x
|
x
|
Warehouse
|
x
|
x
|
General
|
x
|
x
|
Maintenance
|
x
|
x
|
Comments