STANDARD OPERATING PROCEDURE TESTING AND RELEASE OF PACKING MATERIALS
STANDARD
OPERATING PROCEDURE
SUBJECT:
TESTING
AND RELEASE OF
PACKING
MATERIALS
|
DEPARTMENT :
QA
SOP
NO. :
Page
No :
Effective
Date :
Next
Review :
Version
No :
|
1.0 OBJECTIVE:
To provide guidelines for testing and release of
packing materials.
2.0 SCOPE:
Testing of packing materials is done according to
their respective Specifications.
3.0 PROCEDURE:
3.1 After
receiving the GI from the stores, General Manager QA will arrange the sampling
of the consignment. After sampling “UNDER TEST “label shall be pasted on the
consignment.
3.2
The Executive QA / Jr. Executive
responsible for the sampling is witnessed by another QA
Executive
3.3 The
samples will be tested by QA staff; the results of the tested samples should meet individual specification.
3.4 In case
samples are found passing on border line, then exhaustive sampling will be done
and sample will be retested. If necessary a line trails will be conducted for
such samples to assess the machine ability of PM.
3.5
The results are to be documented in
the PM report format (For DRL
only) for record purpose.
3.6 In the
case of rejection or borderline cases a meeting with the supplier through the
purchase department and a deviation report is prepared for record purpose. And
if used under deviation CONDITIONAL APPROVAL is authorized by G.M (Q.A) and
Principal company incharge.
3.7 If the
material is not usable the consignment shall be rejected “REJECTED” Sticker is
affixed and informed to the warehouse for further necessary action. In the case
of loan license the matter is intimated to their representative for further
action.
|
3.8 For all
the approved / rejected consignments the GI will be cleared after preparing the
report and sent back to stores within 10 days with QA details duly filled &
signed.
3.9 Approved
/ rejected stickers will be placed on the containers covering the under test
status of the under test label which have the following details, material name,
QA.No, Recheck on, sign and date.
4.0 FREQUENCY:
As and when new consignment is
received.
5.0 RESPONSIBILITY:
Executive QA/G.M (Q.A).
6.0 REVIEW
GUIDE: Respective Specifications.
7.0 ANNEXURE: 1. Packing
materials analytical report.
2. Status labels.
3.DRL Report format for Packing material.
8.0 SOPs
DISTRIBUTION:
This SOP shall be distributed to following
Departments:
Name of the Department
|
Master Copy
|
Circulatory Copy
|
QA/QC
|
√
|
√
|
Production
|
x
|
x
|
Warehouse
|
x
|
x
|
General
|
x
|
x
|
Maintenance
|
x
|
x
|
Comments